Pneumatic Test Program - Test (MVA)

Preliminary work:
PSE control module voltage supply 23 PSE 1.0, 2.0

Data (mbar)

Test procedure Permissible deviation
Allowable leakage of pneumatic multiple connector, pneumatic lines and vacuum distribution block at 300 mbar vacuum in 1 minute. 30 mbar
Allowable leakage of vacuum distribution block with line at 300 mbar vacuum
in 1 minute.
25 mbar

Preparation for Test:
Vehicles up to approx. 12/93:
1. Disconnect pneumatic multiple connector from PSE control module.
2. Connect tester to bottom side of pneumatic multiple connector at
SRU (MVA) using connector 129 805 04 44.
Vehicles as of approx. 01/94:
1. Disconnect transparent MVA pneumatic line with socket from PSE control module.
2. Connect tester to disconnected pneumatic line using connector
129 805 04 44.
All vehicles:
1. Provide access to vacuum distribution block in right component compartment and pry off all pneumatic lines except transparent
MVA line at connection 1.

Parts Required for Test:
1 Connector 129 805 04 44
1 Connector, 50 mm long 007 997 61 82


Note:
The connections on the PSE control module and pneumatic multiple connector are marked with their German acronyms. In other words:
ZV (German) = CL (English),
SRU (German) = MVA (English),
OSL (German) = OSB (English).


Test scope Test connection Test condition Nominal value Possible cause/Remedy
1.0 Multiple connector, pneumatic line with vacuum distribution block Black connector on tester to connector
SRU on bottom of pneumatic multiple connector.
Apply 300 mbar vacuum to entire system. Vacuum loss
30 mbar in
1 minute.
33 PSE 2.0,

Preparation for Test:
Vehicles up to approx. 12/93:
1. Pry off transparent MVA pneumatic line at pneumatic multiple connector (using a 7 mm open end wrench) .
2. Connect tester to transparent MVA pneumatic line using connector 007 997 61 82.
Vehicles as of approx. 01/94:
1. Disconnect transparent MVA pneumatic line from PSE control module.
2. Connect tester to disconnected pneumatic line using connector
129 805 04 44.
All vehicles:
1. Provide access to vacuum distribution block in right component compartment and pry off all pneumatic lines except transparent
MVA line at connection 1.

Parts Required for Test:
1 Connector, 50 mm long 007 997 61 82
1 Connector 129 805 04 44






Test scope Test connection Test condition Nominal value Possible cause/Remedy
2.0 Vacuum applied to vacuum distribution block and pneumatic line Black connector
on tester.
Apply 300 mbar vacuum to vacuum distribution block and line. Vacuum loss
25 mbar in
1 minute.

Preparation for Test:
1. Remove vacuum distribution block.
2. Connect vacuum/pressure tester to connection 1.

Parts Required for Test:
1 Connector 129 805 04 44
1 Connector, 50 mm long 007 997 61 82






Test scope Test connection Test condition Nominal value Possible cause/Remedy
3.0 Vacuum leakage Black connector
on tester.
Apply 300 mbar vacuum
to vacuum distribution block.
Vacuum loss
25 mbar in
1 minute.
Vacuum distribution block.

Preparation for Test:
1. Connect tester to one end of pneumatic line and plug other end with cap part no. 000 987 29 45.

Notes:
If vacuum is not available at the vacuum distribution block with the PSE control module operating correctly, check the effected line for clogging or kinks.

Parts Required for Test:
1 Cap 000 987 29 45
1 Connector, 50 mm long 007 997 61 82
1 Connector 129 805 04 44




Test scope Test connection Test condition Nominal value Possible cause/Remedy
4.0 Vacuum leakage Black connector
on tester.
Apply 300 mbar vacuum to pneumatic line Vacuum loss
0 mbar in
1 minute.
Pneumatic line.